Crews continue stormwater work in Waynesboro, Pa.

August 29, 2013
  • Crews continue their stormwater work Thursday afternoon on South Potomac Street in Waynesboro, Pa. The work has affected traffic patterns on the busy thoroughfare.
By Jennifer Fitch

WAYNESBORO, Pa. — Next week is expected to be an important one in ongoing stormwater system work in the Borough of Waynesboro.

Crews working on a system bypass along South Potomac Street are expected to install new pipe near the Cemetery Avenue outfall. They are currently lowering a 24-inch sanitary sewer line at Ninth Street, according to Kevin Grubbs, director of borough engineering.

The multimillion-dollar project, which involves several sections of the municipality, is creating changes in traffic patterns.