Sidewalk work on Manor Drive beginning Monday will affect traffic

June 24, 2011

HAGERSTOWN — Road work is scheduled to begin Monday, June 27, on Manor Drive between Dual Highway and Pangborn Boulevard, according to a press release from the city of Hagerstown.

J & P Excavating Company will start the construction of sidewalks on that portion of Manor Drive. The project will require some patching work and excavation on the pavement of the road, so it will affect traffic.

Flaggers will be directing traffic when necessary during the project. There will also be cones, barricades and other traffic control devices. Emergency vehicles will be able to pass through the area while work is going on.

The project is scheduled to begin at 7 a.m. Monday and continue until July 29. Work is expected to be finished each day by 5 p.m.

— Caleb Calhoun, Mobile Journalist