Advertisement

Next culvert replacement project on Crystal Drive set to begin

November 25, 2009

The current culvert replacement project on Crystal Falls Drive near Pondsville Road will be completed on or about Monday and the final in a series of three stream culvert replacement projects is set to begin, the Washington County Division of Public Works Capital Projects Engineering Department said Wednesday.

Work to replace the third and final stream crossing -- approximately two-tenths of a mile north of the intersection of Crystal Falls Drive and Pondsville Road -- is scheduled to begin, and the road will close to through traffic at that location, on or about Dec. 3.

The road closure, required for replacement of a stream culvert pipe crossing under Crystal Falls Drive, will last about 45 days. A detour will be posted to route traffic around the project.

Additional information may be obtained by contacting project manager Jessica Spring at 240-313-2414 or Robert Slocum, deputy director of public works, at 240-313-2418.

Advertisement
The Herald-Mail Articles
|
|
|